Cam Ranh Int’l Port, Cam Ranh, Nha Trang, Vietnam
Commodity: Steel Pipe Pile with coating
Location: Foundation for Anchor piers, support piers and Transitional Bridge
Specifications: TCVN 9245:2012, grade SPP490; 3 layers epoxy coating
Dimensions:
- Ø700mm x t14mm x L24,0m ~ L27,0m (Berth 2)
- Ø800mm x t16mm x L26,0m ~ L36,0m (Berth 3)
Project of Marine service area for mainternance, new building of vessel and petro works with total investment is over 12 billion VND (567 million USD)
Project is in Cam Ranh Bay – Khanh Hoa province, shall be divided into 3 stages.
For 1st stage, Saigon New Port and PVN will cooperate to build Marine service 54ha, with capital of 2,000 billion VND, planning to be operated in Quater I-2016.